PeopleSoft Patches & Fixes for CS 9.0 People Tool Patch 8.49.11
# Task Date Resource Status
1 Refresh CS90QA from CS90PRD June 5 Mike Done
2 Notify SA-team of patching schedule June 16 Lee Done
3 Patch C90DMO and CS90QA June 10-11 Mike Done
4 Functional testing of patches in CS90QA June 12- June 19 PS Functional users Done
5 Freeze project Moves from Development to Production June 19 Mike & Maria Done
6 Patch Campus Solution Production Environment June 20-21 Mike & Maria Done
7 Patch Portal Production Environment June 22-22 Mike & Maria Done
8 Patch Campus Solution Development Environment June 22-23 Mike & Maria  
9 Allow Moves from Development to Production June 24 Mike & Maria  
10 Patch Portal Development Environment June 23-24 Mike & Maria  


Updated:  06/23/08