PeopleSoft Patches & Fixes for May 13, 2006 thru August 01, 2006
# Task Date Resource Status
1 Build documents & prep for patching July 26 - Aug 1 Mike & Maria Done
2 Notify SA-team of patching schedule Aug 1 Lee Done
3 Prepare and Apply Patches to DMO Aug 3 Mike & Maria Done
4 Backup  Security for PRD, PRE, TST, DEV, Aug 7 Gilbert Done
5 Clone PRD to QA July 25 Mike & Maria Done
6 Run Compare Report between DMO & QA 
    (Notify programmers of issues)
Aug 7 Mike & Maria Done
7 Apply patches in QA Aug 7 Mike & Maria Done
8 Security updates for FA Reg. on  QA Aug 7 Gilbert Done
9 Functional testing of patches in QA Aug 8 - 29 PS Functional users Done
10 Freeze project Moves from Development Environment to PRD Aug 30 - 31 Mike & Maria Done 
11 Patch SA801DEV & TST Aug 30 Mike & Maria Done 
12 Patch PRE Aug 31 Mike & Maria Done 
13 Patch SA801PRD (Start at 10:00 pm) Thurs, Aug 31 Mike & Maria Done 
14 Security updates for FA Reg. on PRD Sep. 1 Gilbert Done 
15 Patch SYS Sep 5 Mike & Maria  


Updated:  09/5/2006