PeopleSoft Patches & Fixes for June 26, 2006 thru January 20, 2007

   #

Task Summary

Dates

Resource

Status

 

 

 

 

 

1

Build documents & prep for patching

Jan 22 – Jan 24

Mike

 done

2

Notify SA-Team of patching schedule

Jan 16

Lee

 done

3

Prepare and Apply Patches to SA801DMO

Jan 25 – Jan 26

Maria

done

4

Backup Security for SA801PRD, SA801PRE, SA801TST, SA801DEV, SA801TRN

Jan 29

Gilbert

 done

5

Clone SA801PRD to SA801QA and

Jan 29

Mike

 done

6

Run Compare Reports between SA801DMO & SA801QA

(Notify Programmers of issues)

Jan 29

Mike

done

7

Apply Patches to SA801QA

Jan 30 – Jan 31

Mike

done

8

Security Update on SA801QA

Feb 1

Gilbert

 done  

9

Functional Testing of Patches in SA801QA

Feb 1 – Feb 15

PS Functional Users

done

10

Prepare and Apply Patches to SA801SYS

Feb 1 – Feb 2

Maria

done 

11

Freeze Project Moves from Development Environment to Production

Feb 20 – Feb 27

Mike & Maria

 done 

12

Patch SA801DEV

Feb 20 – Feb 21

Mike

done

13

Patch SA801PRE

Feb 21 – Feb 22

Maria

 done 

14

Patch SA801PRD

Feb 23 – Feb 25

Mike & Maria

 done 

15

Patch SA801TST

Feb 26 – Feb 27

Mike

done 

16

Security Update Patches SA801PRD, SA801PRE, SA801TST, SA801DEV

Feb 27 – Feb 28

Gilbert

done 


Updated:  2/28/2007