PeopleSoft Patches & Fixes for SA8 SP1 Bundle 18 (Regs 3)
# Task Date Resource Status
1 Build documents & prep for patching May 31 Mike Done
2 Notify SA-team of patching schedule June 4 Lee Done
3 Prepare and Apply Patches to DMO May 31 Mike Done
4 Backup  Security for PRD, PRE, TST, DEV, June 4 Gilbert Done
5 Run Compare Report between DMO & QA 
    (Notify programmers of issues)
June 1 Mike Done
6 Apply patches in QA June 1 Mike Done
7 Security updates for FA Reg. on  QA June 4 Gilbert Done
8 Functional testing of patches in QA June 5 - June 7 PS Functional users  
9 Freeze project Moves from Development Environment to PRD June 7 Mike  
10 Patch SA801DEV & TST June 8 Mike  
11 Patch PRE June 8 Mike  
12 Patch SA801PRD (Start at 6:00 am) June 8 Mike  
13 Security updates for FA Reg. on PRD June 11 Gilbert  
14 Patch SYS June 1 Mike Done


Updated:  06/04/07