| Tasks | Date | Resource | Status |
| Notify SA-Team of Patching Schedule | 4/14/2008 | Lee | done |
| Build Documentation & prep for patching | 4/14 - 4/18 | Mike/Maria | done |
| Prepare and apply patches to DMO | 4/18/2008 | Maria | done |
| Run compare reports between DMO & QA (notify programmers of issues found) | 4/18/2008 | Maria | done |
| Apply patches in QA | 4/18/2008 | Mike | done |
| Security Updates for FA Reg on QA | 4/18/2008 | Gilbert | done |
| Functional Testing of patches | 4/23 - 4/30 | PS functional users | done |
| User Security backup in CS90PRD | 5/1/2008 | Gilbert | done |
| Patch CS90PRD | Friday 5/2/08 | Mike/Maria | done |
| Security Updates for FA Reg on CS90PRD | Friday 5/2/08 | Gilbert | done |
| Freeze Project moves from Development environment to PRD | Friday 5/2/08 | Mike/Maria | done |
| Clone PRE & TST | 5/5/08 | Mike/Maria | done |
| Patch DEV | 5/7/08 | Mike/Maria | done |