PeopleSoft Patches & Fixes for Nov 5, 2005 thru Jan 24, 2006
# Task Date Resource Status
1 Finish building documents & prep for patching Jan 24- 30 Mike & Maria Done
2 Prepare DMO environment for patching Jan 30 Mike & Maria Done
3 Apply Patches to DMO Jan 31- Feb1 Mike & Maria Done
4 Backup PRD, PRE, TST, DEV, MIS Feb 1 Gilbert Done
5 Clone PRD to QA Feb 2 Mike & Maria Done
6 Run Compare Report between DMO & QA 
    (Notify programmers of issues)
Feb 2 Mike & Maria Done
7 Apply patches in QA Feb 3 - 6 Mike & Maria Done
8 Notify SA-team with regarding patching schedule Jan 24 Lee Done
9 Security updates for FA Reg.1 for 06-07 on  QA Feb 6 Gilbert Done
10 Functional testing of patches in QA Feb 7 - 13 Mike & Maria Done
11 Freeze project Moves from TST to PRD Feb 21 - 27 Mike & Maria Done
12 Patch SA801DEV Feb 21 - 22 Mike & Maria Done
13 Patch SA801TST Feb 22 - 23 Mike & Maria Done
14 Patch SA801PRD (start at NOON) Feb 24  Mike & Maria Done
15 Security updates for FA Reg.1 for 06-07 on PRD Feb 27 Gilbert Done
16 Backup MIS & PRE security Feb 23 Gilbert Done
17 Clone SA801MIS from PRD March 1 -2 Mike & Maria Done
18 Restore MIS Security March 3 Gilbert Done
19 Clone SA801PRE from PRD March 6 Mike & Maria Done
20 Restore PRE Security March 6 Gilbert Done
21 Patch SYS March 28 Mike & Maria Done


Updated:  03/28/2006