PeopleSoft Patches & Fixes for Jan 25, 2006 thru May 12, 2006
# Task Date Resource Status
1 Build documents & prep for patching May 8 - 12 Mike & Maria Done
2 Prepare and Apply Patches to DMO May 15 - 16 Mike & Maria Done
3 Backup PRD, PRE, TST, DEV, May 16 Gilbert Done
4 Clone PRD to QA May 17 Mike & Maria Done
5 Run Compare Report between DMO & QA 
    (Notify programmers of issues)
May 17 Mike & Maria Done
6 Apply patches in QA May 18 Mike & Maria Done
7 Notify SA-team of patching schedule May 5 Lee Done
8 Security updates for FA Reg.2 for 06-07 on  QA May 19 Gilbert Done
9 Functional testing of patches in QA May 22 - June 2 PS Functional users Done
10 Freeze project Moves from Development Environment to PRD June 5 - 12 Mike & Maria Done
11 Patch SA801DEV June 5 - 6 Mike & Maria Done
12 Patch SA801PRE June 7 - 8 Mike & Maria Done
13 Backup SA801TST security June 8 Gilbert Done
14 Patch SA801PRD (start at NOON) June 9 Mike & Maria Done
15 Security updates for FA Reg. 3 for 06-07 on PRD June 12 Gilbert Done
16 Clone SA801TST from PRD June 12 - 13 Mike & Maria Done
17 Restore SA801TST Security June 13 Gilbert Done
18 Patch SYS June 13 - 14 Mike & Maria Done


Updated:  06/12/2006