PeopleSoft Patches & Fixes for 7/3/04 - 11/5/04 & 1/21/05
# Task Date Resource Status
1 Finish building documents and prep for Patching Nov 8-9 Mike & Maria done
2 Apply group 1 Patches to DMO Nov 10-12 Mike & Maria done
3 Clone PRE to QA   Mike & Maria done
4 Run Compare Report between DMO & QA  (Notify Programmers of any issues) Nov 15 Mike & Maria  done - 1 menu item shown
5 Backup QA Nov 16 Mike & Maria done
6 Apply patches in QA Nov 16-17 Mike & Maria  done
7 Clone TRN from patched QA Nov 16-17 Mike & Maria done
8 Clone PRE from PRD (after phase 1 implementation) Dec 23 Mike done
9 Finish building documents & prep for group 2 patches Jan 21 Mike & Maria  done
10 Apply patches to DMO Jan 21 Mike & Maria  done
11 Apply patches to SYS Jan 21 Mike & Maria done
12 Freeze production of any change migrations Jan 21 All done
13 Clone PRD to QA Jan 21 Mike & Maria done
14 Run Compare Report between DMO & QA;  review w/ developers as necessary Jan24 Mike & Maria done
15 Backup QA Jan 24 Mike & Maria done
16 Apply patches to QA Jan 24 Mike & Maria done
17 Setup security for QA Jan 24 Gilbert done
18 Test patches in QA Jan 24 -  27 Daryl, Stephen, Keenan  notified 1/25 by Lee
19 Functional testing of patches in QA Jan 24 -  28 Super Users   notified 1/25 by Lee
20 Delete TRN (backup security) Feb 7 Mike & Maria done
21 Clone TRN from patched PRE Feb 7 Mike & Maria done
22 Backup security for PRE & freeze moves to PRE Feb 4 Gilbert done
23 Backup PRE before patching Mike & Maria  done
24 Patch PRE Feb 7 Mike & Maria  done
25 Test patches & phase 2 in PRE Feb 7 - Feb 15 Daryl, Stephen, Keenan, & users in progress
26 Notify Payroll & H/R with regards to patching Production Feb 8 Lee done
27 Backup security for CNV Feb 9 Gilbert done
28 Clone CNV from patched PRE & move to BAM Feb 9 Mike & Maria done
29 Backup security for PRD, DEV, & TST Feb 15 Gilbert done
30 Production Unavailable Feb 16 All done
31 Backup PRD before patching Mike & Maria  done
32 Patch PRD beginning on Wednesday morning Feb 16 Mike & Maria done
33 Move projects from PRE to PRD Feb 17 to go-live Mike & Maria  done
34 Run Compare Reports between DMO & {DEV, TST} & review w/ developers as necessary Feb 17 Mike & Maria  done
35 Freeze migration in development environment Feb 18 All  done
36 Backup DEV before patching Mike & Maria done
37 Patch DEV beginning on Friday Feb 18 Mike & Maria  done
38 Backup TST before patching Mike & Maria  done
39 Patch TST beginning on Saturday Feb 19 Mike & Maria done 

If all goes according to plan without any complications this is the best case scenario & falls very close to go-live.
Updated:  03/11/2005