PeopleSoft Patches & Fixes for 01/21/05 - 4/29/05

#

Task

Date

Resource

Status

1

Finish building documents patches

May 6

Mike & Maria

Done

2

Apply patches to DMO

May 9

Mike & Maria

Done

3

Create Patches & Fixes Template

May 10

Mike & Maria

Done

4

Notify Payroll & H/R with regards to patching Production

May 11

Lee

Done

5

Apply patches to SYS

May 10

Mike & Maria

Done

6

Clone PRD to QA

May 12

Mike & Maria

Done

7

Run Compare Report between DMO & QA;  review w/ developers as necessary

May 12

Mike & Maria

Done

8

Backup QA & apply patches to QA

May 16

Mike & Maria

Done

9

Setup security for QA

May 16

Gilbert

Done

10

Functional testing of patches in QA

May 17 - June 2

Super Users, PayRoll, HR, & Ciber

Done

11

Run Compare Reports between DMO & {PRE, DEV, TST & MIS} & review w/ developers as necessary

June 3

Mike

Done 

12

Backup security for , DEV, TST, CNV, MIS, PRE, PRD, & TRN

June 6

Gilbert

Done 

13

Freeze migration to PRD from Development Env.

June 3 - 10

Mike

Done 

14

Backup & Patch PRE

Fri, June 7

Mike

Done 

15

Backup & Patch DEV

Sat, June 8

Mike

Done 

16

Backup & Patch  TST

Sun, June 9

Mike

Done 

17

Backup & Patch MIS

Thu, June 16

Mike

Done 

18

Backup & Patch PRD

Fri, June 17

Mike

Done 

19

Clone TRN & CNV from PRD

 

Mike

Done

20

Restore security to new TRN & CNV

 

Gilbert

Done