PeopleSoft Patches & Fixes for Aug 20, 2005 thru Nov 4, 2005
# Task Date Resource Status
1 Finish building documents and prep for Patching Oct 31 - Nov 4 Mike & Maria Done
2 Apply Patches to DMO Nov 7 - 11 Mike & Maria Done
3 Clone PRD to QA  Nov 22 Mike & Maria Done
4 Run Compare Report between DMO & QA  (Notify Programmers of any issues) Nov 23 Mike & Maria Done
5 Apply patches in QA Nov 23-28 Mike & Maria Done
6 Notify Payroll & H/R with regards to patching Production Nov 28 Lee Done
7 Setup security for QA Nov 29 Gilbert N/A
8 Functional testing of patches in QA Dec 5 - 9 Mike & Maria Done
9 Freeze project Moves between Different PeopleTools versions Dec 12 - 26 Mike & Maria  
10 Update PeopleTools 8.20 to 8.22.x Web Server Dec 16 Mike & Maria Done
11 Patch SA801PRD Sat. Dec 17 - Sun Dec 18 Mike & Maria Done
12 Patch SA801CNV Dec 19 - 20 Mike & Maria Done
13 Patch SA801PRE Dec 19 - 20 Mike & Maria Done
14 Patch SA801DEV Dec 19 - 20 Mike & Maria Done
15 Patch SA801TST Dec 21 - 22 Mike & Maria Done
16 Clone MIS from SA801PRD Jan 3 Mike & Maria Done
17 Clone TST from SA801PRD Jan 3 Mike & Maria Done


Updated:  1/4/06