Patch Schedule 2/10/20 -5/7/20 : CS PUM 17 and HR Bundles
# | Task | Date | Resource | Status |
---|---|---|---|---|
1 | Notify SA-team of patching schedule | 4/20 | Patrick | Completed |
2 | Prep for patches/fixes |
4/29 - |
DBAs | Completed |
3 | Apply PUM 17 to DMO (CS), Bundle DMO (HR) | 5/4 - 5/5 |
DBAs | Completed |
4 | Backup Security for QA, DEV, TST (CS/HR) | 5/5 | Gilbert | Completed |
5 | Refresh QA (CS/HR) | 5/6 | DBAs | Completed |
6 | Run Compare Report between DMO & QA (CS/HR) (Notify programmers of issues) |
5/6 | DBAs | Completed |
7 | Apply patches in QA (CS/HR) | 5/7 - 5/8 | DBAs | Completed |
8 | Security updates for FA Reg. on QA (CS/HR) | 5/8 | Gilbert | Completed |
9 | Freeze project Moves from Development to PRD (CS/HR) | 5/6 - 6/17 | Programmers | Completed |
10 | Functional testing of patches in QA (CS/HR) | 5/11 - 5/29 | Functional Users | Completed |
11 | Apply PUM 17 to PRD (CS), Bundles PRD (HR) (Start at noon) | 6/5 - 6/7 | DBAs | Completed |
12 | Apply security for PRD (CS/HR) | 6/5 - 6/7 | Gilbert | Completed |
13 | Refresh DEV from PRD (CS/HR) | 6/10 - 6/11 | DBAs | Completed |
14 | Apply security for DEV (CS/HR) | 6/10 - 6/11 | Gilbert | Completed |
15 | Refresh TSTfrom PRD (CS/HR) | 6/15 - 6/16 | DBAs | Completed |
16 | Apply security for TST (CS/HR) | 6/16 - 6/17 | Gilbert | Completed |