Patch Schedule - :CS PUM 38 and HR PUM 55

 

# Task Date Resource Status
1 Notify SA-team of patching schedule      
2 Prep for patches/fixes June 2- 3 DBAs   Completed
3 Backup Appsian QA (CS/HR/PORTAL) June 3 Security Admin  
4 Apply  PUM to DMO  June 3 -  9 DBAs  
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

June 10 - July 27 Programmers In progress
6 Refresh QA (CS/HR)   June 10 - June 12 DBAs Completed
7 Apply PUM to QA   June 15 - 18th DBAs In progress
8 Run Compare Report between DMO & QA 
(Notify programmers of issues)
June 17 DBAs  
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR) June17 Security Admin  
10 SA Team Group -  Enable QA Portal Guard Tiles    Javier  
11

Functional testing of patches in QA 

June 22 - July 10 Functional Users  
12 SA Team Group - Remove QA Portal Guard Tiles    Javier  
13 Apply PUM TO PRD (Starting 2 pm) July 17 -19 DBAs  
14 Apply security for PRD (CS/HR) July 18th Security Admin  
15 Backup Appsian/PS security DEV and TST (CS,HR,)   Security Admin  
16 Refresh TST from PRD (CS/HR)  July 22 - 29  DBAs  
17 Apply security for TST (CS/HR)    July 29 Security Admin  
18 Refresh DEV from PRD (CS/HR)  July 30 - Aug 3    
  Apply security for TST (CS/HR) Aug 3 Security Admin  

Created: 04/14/2026
Updated:  6/17/2026