Patch Schedule - :CS PUM 39 and HR PUM

 

# Task Date Resource Status
1 Notify SA-team of patching schedule      
  Apply CX project to QA 

Oct 16th 

DBAs, Security admin, programmer  
  CX Functional testing in QA

Oct 19 - 
Nov 13

Functional Users  
  Prep for patches/fixes

Oct 26 - 30

DBAs  
4 Apply  PUM to DMO  Nov 2 -
Nov 5
DBAs  
6 CX migration from QA to PRD (Starting at 2pm) Nov 20 DBAs, Security admin, programmer  
7

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

Nov 25 -
March 1

Programmers  
8 Refresh QA (CS/HR)   Nov 30 -
Dec 1
DBAs  
9 Apply PUM to QA   Dec 2 - 4 DBAs  
10 Run Compare Report between DMO & QA 
(Notify programmers of issues)
Dec 3 DBAs  
11 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR) Dec 3 Security Admin  
12 SA Team Group -  Enable QA Portal Guard Tiles    Javier  
13

Functional testing of patches in QA 

Dec 7 -
Feb 10
Functional Users  
14 Prep Production HR/CS for PUM implementation Feb 11 - 18 DBAs  
15 Apply PUM TO PRD (Starting 2 pm) Feb 19 - 21 DBAs  
16 Apply security for PRD (CS/HR) Feb 20 Security Admin  
17 Backup Appsian/PS security DEV and TST (CS,HR,)   Security Admin  
18 Refresh DEV from PRD (CS/HR)  Feb 24 - 25  DBAs  
19 Apply security for DEV (CS/HR)    Feb 25 Security Admin  
20 Refresh TST from PRD (CS/HR)  March 2 - 3 DBAs  
21 Apply security for TST (CS/HR) March 3 Security Admin  