Non-Instructional Program Review Timeline
The table below outlines the timeline to help successfully guide the completion of the non-instructional program review self-study report.
| Action | Responsibility | TImeline/Deadline |
|---|---|---|
|
Program Notified of Review |
IERPG |
March 15th – April 1st |
| Program Review Planning Form |
Department or Program Manager |
April 15th |
| Orientation |
IERPG |
April 15th – April 25th |
| Program Review Committee Formed | Department or Program Manager | May 5th |
| Program Review Committee Orientation |
IERPG Program Review Committee |
May |
| Program Review Committee Form | Department or Program Manager Program Review Committee |
May 31st |
| Self-Study: Data analysis and report preparation |
Writing Committee |
June - October |
| Self Study Submitted | Department or Program Manager | October 31st |
| Committee Feedback and Meeting |
Program Review Committee |
By December 1st |
| Committee Feedback Integration | Writing Committee | December – January 10th |
| Finalized Self-Study Submitted | Department or Program Manager | January 10th |
| Approval | Program Review Committee | January 30th |
| Coordinating and Planning and Budget Committee report outs | IERPG | May |
*Note: if the deadline falls on a holiday or weekend, the deadline is the next business day