Patch Schedule - : CS PUM 34, PRP 1-3 and HR PUM 51

 

# Task Date Resource Status
1 Notify SA-team of patching schedule Mar 21 Patrick  
2 Prep for patches/fixes Apr 21 - 28 DBAs    
3 Backup Appsian QA (CS/HR/PORTAL) Apr 29 Security Admin  
4 Apply HR PUM 51 to DMO HR Apr 30 - May 6 DBAs  
4 Apply CS PUM 34, PRP 1 - 3 to DMO CS Apr 30- May 6  DBAs  
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

May 7 - Aug 6 Programmers  
6 Refresh QA (CS/HR)   May 7  DBAs Complete
7 Apply CS  PUM 34, PRP 1 - 3  and HR PUM 51 to QA (CS/HR),  May 12 - 16 DBAs Complete
8 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
May 19 DBAs Complete
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) May 19-20 Security Admin Complete
10 SA Team Group -  Enable QA Portal Guard Tiles  May 20 Javier  
11

Functional testing of patches in QA (CS/PORTAL)

 May 21 -  July 18 Functional Users Complete
12 SA Team Group - Remove QA Portal Guard Tiles    Javier  
13 Apply CS PUM34, PRP 1-3 and HR PUM 51 to PRD (Starting 2 pm) July 25 DBAs Complete
14 F5 Cloud Cutover (8pm) July 27 Marc  
15 Apply security for PRD (CS/HR) July 27 Security Admin Complete
16 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) July 29 Security Admin Complete
17 Refresh DEV from PRD (CS/HR)  July 30  DBAs Complete
18 Apply security for DEV (CS/HR)    Aug 1 Security Admin Complete
19 Refresh TST from PRD (CS/HR)  Aug 4  DBAs Complete
20 Apply security for TST (CS/HR) Aug 6 Security Admin Complete

Created: 03/18/2025
Updated: 08/06/2025