Patch Schedule - : CS PUM 35-36 and HR PUM 52

 

# Task Date Resource Status
1 Notify SA-team of patching schedule Sept 14 Patrick  
2 Prep for patches/fixes Sep 23 -26 DBAs    
3 Backup Appsian QA (CS/HR/PORTAL) Sep 29 Security Admin  
4 Apply HR PUM 52 to DMO HR Sep 30 - Oct 2 DBAs  
4 Apply CS PUM 35-36 to DMO CS Sep 30 - Oct 2 DBAs  
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

Oct 3 - Nov 20 Programmers  
6 Refresh QA (CS/HR)   Oct 3  DBAs Complete
7 Apply CS  PUM 35-36  and HR PUM 52 to QA (CS/HR),  Oct 6 - 8 DBAs Complete
8 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
Oct 8 DBAs Complete
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) Oct 9 Security Admin Complete
10 SA Team Group -  Enable QA Portal Guard Tiles  Oct 9 Javier  
11

Functional testing of patches in QA (CS/PORTAL)

 Oct 13 -           Oct 31 Functional Users Complete
12 SA Team Group - Remove QA Portal Guard Tiles    Javier  
13 Apply CS PUM35-36 and HR PUM 52 to PRD (Starting 2 pm) Nov 7 - 9 DBAs Complete
14 Apply security for PRD (CS/HR) Nov 9 Security Admin Complete
15 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) Nov 10 Security Admin Complete
16 Refresh DEV from PRD (CS/HR)  Nov 13 -14  DBAs Complete
17 Apply security for DEV (CS/HR)    Nov 14 Security Admin Complete
18 Refresh TST from PRD (CS/HR)  Nov 19 - 20  DBAs Complete
19 Apply security for TST (CS/HR) Nov 20 Security Admin Complete

Created: 09/03/2025
Updated:11/20/2025