Patch Schedule 02/05/19 - 11/07/19 : CS PUM 15 and HR Bundles

 

# Task Date Resource Status
1 Notify SA-team of patching schedule 10/18 Patrick  Notified
2 Prep for patches/fixes 10/30 - 10/31 DBAs   Complete
3 Apply PUM 15 to DMO (CS), Bundle DMO (HR) 10/30 - 10/31 DBAs Complete
4 Backup Security for QA, DEV, TST (CS/HR) 10/30 Gilbert  
5 Refresh QA (CS/HR) 11/1 - 11/6 DBAs Complete
6 Run Compare Report between DMO & QA (CS/HR)
(Notify programmers of issues)
11/6 DBAs Complete
7 Apply patches in QA (CS/HR) 11/8-11/12 DBAs Complete
8 Security updates for FA Reg. on QA (CS/HR) 11/12 Gilbert Complete
9 Freeze project Moves from Development to PRD (CS/HR) 11/7 - 12/18  Programmers Complete
10 Functional testing of patches in QA (CS/HR) 11/14 - 12/3 Functional Users Complete
11 Apply PUM 15 to PRD (CS), Bundles PRD (HR)                                                               (Start at noon) 12/6 - 12/8 DBAs Complete
12 Apply security for PRD (CS/HR) 12/8  Gilbert Complete
13 Refresh DEV from PRD (CS/HR)  *Original dates Dec 12 - 13  12/10   DBAs Complete
14 Apply security for DEV (CS/HR)   *Original dates Dec 13  12/10-11 Gilbert Complete
15 Refresh TSTfrom PRD (CS/HR) 12/16 - 12/17  DBAs  Complete
16 Refresh TST from PRD (CS/HR) 12/17 Gilbert  Complete

Created:  10/04/19
Updated: 12/17/19