Patch Schedule - : CS PUM (FA Regs )

 

# Task Date Resource Status
1 Notify SA-team of patching schedule Jan 2023 Patrick completed
2 Prep for patches/fixes June 5 - 6 DBAs   completed
3 Backup Appsian QA (CS/HR/PORTAL) June 7 Security Admin completed
4 Apply PUM 29 to DMO (CS), Bundle DMO (HR) June 7 DBAs completed
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

June 8 -  July 24

Programmers  
6 Refresh QA (CS/HR/PORTAL)   June 8 DBAs Completed
7 Apply patches in QA (CS/HR) 

June 9 - 12

DBAs completed
8 Run Compare Report between DMO & QA (CS/HR)
(Notify programmers of issues)
June 12 DBAs completed
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) June 12 - 15 Security Admin  
10 SA Team Group -  Enable QA Portal Guard Tiles  June 16 Javier  
11 Functional testing of patches in QA (CS/HR/PORTAL)

June 19 - July 7

Functional Users completed
12 Resolve  issues related to PUM implementation in QA July 10 - 13 DBAs/Developers  
13 SA Team Group - Remove QA Portal Guard Tiles  July 14 Javier  
14 Apply PUM 29 to PRD (CS), Bundles PRD (HR) 
(Starting at 2pm)              
July 14 - 16 DBAs completed
15 Apply security for PRD (CS/HR) July 15 - 16 Security Admin completed
16 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) July 18 Security Admin completed
17 Refresh DEV from PRD (CS/HR/PORTAL)   July 19  DBAs completed
18 Apply security for DEV (CS/HR/PORTAL)    July 19 -20 Security Admin completed
19 Refresh TST from PRD (CS/HR/PORTAL) July 24  DBAs completed
20 Apply security for TST (CS/HR/PORTAL) July 24 - 25 Security Admin completed

Created: 01/18/23
Updated: 07/26/23