HR Upgrade Patch Schedule

 

# Task Date Resource Status
1 Notify SA-team of patching schedule   Patrick  
2

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

Jan 26  -
Feb 8
Programmers In progress
3 Functional testing of patches in QA (CS/PORTAL) Dec 13 - 
Jan 22
Functional Users Done
4 HR 9.2 Production Upgrade Jan 27-28 DBAs Done
5 Backup Appsian/PS security DEV and TST, QA (CS,HR,PORTAL) Jan 30 Security Admin Done
6 Refresh DEV from PRD (CS/HR/PORTAL)  Jan 31 - Feb 1  DBAs Done
7 Apply security for DEV (CS/HR/PORTAL)    Feb 1  Security Admin Done
8 Refresh TST from PRD (CS/HR/PORTAL)  Feb 5 - 6  DBAs Done
9 Apply security for TST  (CS/HR/PORTAL)   Feb 6 Security Admin Done
10 Refresh QA from PRD  (CS/HR/PORTAL)  Feb 8- 9  DBAs  
11 Apply security for QA   (CS/HR/PORTAL) Feb 9 Security Admin  

Created: 1/12/24
Updated: 2/6/24