Patch Schedule - : CS PUM (FA Regs )

 

# Task Date Resource Status
1 Notify SA-team of patching schedule      
2 Prep for patches/fixes March 18-19 DBAs   Complete
3 Backup Appsian QA (CS/HR/PORTAL) March 19 Security Admin  
4 Apply CS PUM 31/HR PUM 48 to DMO (CS/HR),  March 19 - 22 DBAs Complete
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

March 25 - May 7 Programmers In progress
6 Refresh QA (CS/HR/PORTAL)   March 25 -26 DBAs Complete
7 Apply CS PUM 31/HR PUM 48 to QA (CS/HR),  March 27- 29   Complete
8 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
March 29 DBAs Complete
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) March 29 Security Admin  
10 SA Team Group -  Enable QA Portal Guard Tiles  March 29 Javier  
11

Functional testing of patches in QA (CS/PORTAL)

 

April 1-19

Functional Users Complete
12 SA Team Group - Remove QA Portal Guard Tiles    Javier  
13 Apply CS PUM 31/HR PUM 48 to PRD April 26-28 DBAs Complete
14 Apply security for PRD (CS/HR) April 28 Security Admin  
15 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) April 30 Security Admin  
16 Refresh DEV from PRD (CS/HR/PORTAL)  May 1 - 2  DBAs  
17 Apply security for DEV (CS/HR/PORTAL)    May 2 Security Admin  
18 Refresh TST from PRD (CS/HR/PORTAL)  May 6 - 7  DBAs  
19 Apply security for TST (CS/HR/PORTAL) May 7 Security Admin  

Created: 01/16/24