Patch Schedule - : CS PUM (FA Regs )
# | Task | Date | Resource | Status |
---|---|---|---|---|
1 | Notify SA-team of patching schedule | |||
2 | Prep for patches/fixes | May 28 | DBAs | |
3 | Backup Appsian QA (CS/HR/PORTAL) | May 30 | Security Admin | |
4 | Apply CS Post Regs 2, PRP 5, 6, 7 to DMO (CS/HR), | June 4 - 6 | DBAs | |
5 |
Freeze project Moves from Development to PRD (CS/HR/PORTAL)
|
June 6 - July 23 | Programmers | In Progress |
6 | Refresh QA (CS/HR/PORTAL) | June 6 - 10 | DBAs | complete |
7 | Apply CS Post Regs 2, PRP 5, 6, 7 to QA (CS/HR), | June 11 - 14 | complete | |
8 | Run Compare Report between DMO & QA (CS) (Notify programmers of issues) |
June 12 | DBAs | complete |
9 | Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) | June 14 | Security Admin | complete |
10 | SA Team Group - Enable QA Portal Guard Tiles | June 14 | Javier | |
11 |
Functional testing of patches in QA (CS/PORTAL) |
June 17 - July 8 | Functional Users | complete |
12 | SA Team Group - Remove QA Portal Guard Tiles | Javier | ||
13 | Apply CS Post Regs 2, PRP 5, 6, 7 to PRD | July 12 - 14 | DBAs | complete |
14 | Apply security for PRD (CS/HR) | July 13 | Security Admin | |
15 | Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) | July 16 | Security Admin | complete |
16 | Refresh DEV from PRD (CS/HR/PORTAL) | July 17 -18 | DBAs | complete |
17 | Apply security for DEV (CS/HR/PORTAL) | July 18 | Security Admin | complete |
18 | Refresh TST from PRD (CS/HR/PORTAL) | July 25-26 | DBAs | |
19 | Apply security for TST (CS/HR/PORTAL) | July 26 | Security Admin |
Created: 04/30/2024
Updated: 7/23/2024