Patch Schedule - : CS PUM (FA Regs )

 

# Task Date Resource Status
1 Notify SA-team of patching schedule      
2 Prep for patches/fixes May 28 DBAs    
3 Backup Appsian QA (CS/HR/PORTAL) May 30 Security Admin  
4 Apply CS Post Regs 2, PRP 5, 6, 7 to DMO (CS/HR),  June 4 - 6 DBAs  
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

June 6 - July 23 Programmers In Progress
6 Refresh QA (CS/HR/PORTAL)   June 6 - 10 DBAs complete
7 Apply CS  Post Regs 2, PRP 5, 6, 7 to QA (CS/HR),  June 11 - 14   complete
8 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
June 12 DBAs complete
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) June 14 Security Admin complete
10 SA Team Group -  Enable QA Portal Guard Tiles  June 14 Javier  
11

Functional testing of patches in QA (CS/PORTAL)

June 17 - July 8 Functional Users complete
12 SA Team Group - Remove QA Portal Guard Tiles    Javier  
13 Apply CS Post Regs 2, PRP 5, 6, 7 to PRD July 12 - 14 DBAs complete
14 Apply security for PRD (CS/HR) July 13 Security Admin  
15 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) July 16 Security Admin complete
16 Refresh DEV from PRD (CS/HR/PORTAL)  July 17 -18  DBAs complete
17 Apply security for DEV (CS/HR/PORTAL)    July 18 Security Admin complete
18 Refresh TST from PRD (CS/HR/PORTAL)  July 25-26  DBAs  
19 Apply security for TST (CS/HR/PORTAL) July 26 Security Admin  

Created: 04/30/2024
Updated:  7/23/2024