Patch Schedule - : CS PRP (FA critical Fix)

 

# Task Date Resource Status
1 Notify SA-team of patching schedule July 18 Patrick  
2 Prep for patches/fixes: CSPUM32 server July 18-23 DBAs   completed
3 Backup Appsian QA (CS/HR/PORTAL) July 19 Security Admin  
4

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

July 22 -

Aug 7

Programmers Complete
5 Refresh QA (CS/HR/PORTAL)   July 22-23 DBAs completed
6 Apply CS PRP to QA (CS/HR),  July 23  DBAs completed
7 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
July 23 DBAs  
8 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) July 23 Security Admin completed
9 SA Team Group -  Enable QA Portal Guard Tiles  July 23 Javier completed
10

Functional testing of patches in QA (CS/PORTAL)

 

July 23 - 26

Functional Users completed
11 SA Team Group - Remove QA Portal Guard Tiles    Javier  
12 Apply CS PRP to PRD starting at 8:00am Sunday July 28th DBAs completed
13 Apply security for PRD (CS/HR) * July 28 Security Admin completed
14 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) July 29 Security Admin completed
15 Refresh TST from PRD (CS/HR/PORTAL)  July 31 - Aug 1  DBAs completed
16 Apply security for TST (CS/HR/PORTAL)    Aug 1 Security Admin completed
17 Refresh DEV from PRD (CS/HR/PORTAL)  Aug 6 - 7  DBAs completed
18 Apply security for DEV (CS/HR/PORTAL) Aug 7 Security Admin completed

Created: 07/18/24