Patch Schedule - : CS PRP (FA critical Fix)
# | Task | Date | Resource | Status |
---|---|---|---|---|
1 | Notify SA-team of patching schedule | July 18 | Patrick | |
2 | Prep for patches/fixes: CSPUM32 server | July 18-23 | DBAs | completed |
3 | Backup Appsian QA (CS/HR/PORTAL) | July 19 | Security Admin | |
4 |
Freeze project Moves from Development to PRD (CS/HR/PORTAL)
|
July 22 - Aug 7 |
Programmers | Complete |
5 | Refresh QA (CS/HR/PORTAL) | July 22-23 | DBAs | completed |
6 | Apply CS PRP to QA (CS/HR), | July 23 | DBAs | completed |
7 | Run Compare Report between DMO & QA (CS) (Notify programmers of issues) |
July 23 | DBAs | |
8 | Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) | July 23 | Security Admin | completed |
9 | SA Team Group - Enable QA Portal Guard Tiles | July 23 | Javier | completed |
10 |
Functional testing of patches in QA (CS/PORTAL)
|
July 23 - 26 |
Functional Users | completed |
11 | SA Team Group - Remove QA Portal Guard Tiles | Javier | ||
12 | Apply CS PRP to PRD starting at 8:00am | Sunday July 28th | DBAs | completed |
13 | Apply security for PRD (CS/HR) * | July 28 | Security Admin | completed |
14 | Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) | July 29 | Security Admin | completed |
15 | Refresh TST from PRD (CS/HR/PORTAL) | July 31 - Aug 1 | DBAs | completed |
16 | Apply security for TST (CS/HR/PORTAL) | Aug 1 | Security Admin | completed |
17 | Refresh DEV from PRD (CS/HR/PORTAL) | Aug 6 - 7 | DBAs | completed |
18 | Apply security for DEV (CS/HR/PORTAL) | Aug 7 | Security Admin | completed |