Patch Schedule - : CS PUM 33 and HR PUM 50
# | Task | Date | Resource | Status |
---|---|---|---|---|
1 | Notify SA-team of patching schedule | Sept 13 | Patrick | complete |
2 | Prep for patches/fixes | Sept 17 | DBAs | complete |
3 | Backup Appsian QA (CS/HR/PORTAL) | Sept 18 | Security Admin | complete |
4 | Apply HR PUM 50 to DMO HR | Sept 23 | DBAs | complete |
Apply CS PUM 33 to DMO CS | Sept 24 | DBAs | complete | |
5 |
Freeze project Moves from Development to PRD (CS/HR/PORTAL)
|
Sept 19 - Nov 15 | Programmers | IN PROGRESS |
6 | Refresh QA (CS/HR/PORTAL) | Sept 19 - 20 | DBAs | complete |
7 | Apply CS PUM 33 and HR PUM 50 to QA (CS/HR), | Sept 24 - Oct 2 | DBAs | complete |
8 | Run Compare Report between DMO & QA (CS) (Notify programmers of issues) |
Oct 2 | DBAs | complete |
9 | Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) | Oct 2 | Security Admin | complete |
10 | SA Team Group - Enable QA Portal Guard Tiles | Oct 2 | Javier | complete |
11 |
Functional testing of patches in QA (CS/PORTAL) |
Oct 3 - 24 | Functional Users | complete |
12 | SA Team Group - Remove QA Portal Guard Tiles | Nov 1 | Javier | |
13 | Apply CS PUM33 and HR PUM 50 to PRD (Starting 2 pm) | Nov 1 | DBAs | complete |
14 | Apply security for PRD (CS/HR) | Nov 3 | Security Admin | complete |
15 | Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) | Nov 4 | Security Admin | complete |
16 | Refresh DEV from PRD (CS/HR/PORTAL) | Nov 7 -8 | DBAs | complete |
17 | Apply security for DEV (CS/HR/PORTAL) | Nov 12 | Security Admin | complete |
18 | Refresh TST from PRD (CS/HR/PORTAL) | Nov 13 - 14 | DBAs | In progress |
19 | Apply security for TST (CS/HR/PORTAL) | Nov 15 | Security Admin |