Patch Schedule - : CS PUM 33 and HR PUM 50

 

# Task Date Resource Status
1 Notify SA-team of patching schedule Sept 13 Patrick complete
2 Prep for patches/fixes Sept 17 DBAs   complete
3 Backup Appsian QA (CS/HR/PORTAL) Sept 18 Security Admin complete
4 Apply HR PUM 50 to DMO HR Sept 23 DBAs complete
  Apply CS PUM 33 to DMO CS Sept 24 DBAs complete
5

Freeze project Moves from Development to PRD (CS/HR/PORTAL)

 

Sept 19 - Nov 15 Programmers IN PROGRESS
6 Refresh QA (CS/HR/PORTAL)   Sept 19 - 20 DBAs complete
7 Apply CS  PUM 33 and HR PUM 50 to QA (CS/HR),  Sept 24 -  Oct 2 DBAs complete
8 Run Compare Report between DMO & QA (CS)
(Notify programmers of issues)
Oct 2 DBAs complete
9 Security updates for FA Reg.& Appsian RuleSets on QA (CS/HR/PORTAL) Oct 2 Security Admin complete
10 SA Team Group -  Enable QA Portal Guard Tiles  Oct 2 Javier complete
11

Functional testing of patches in QA (CS/PORTAL)

Oct 3 -  24 Functional Users complete
12 SA Team Group - Remove QA Portal Guard Tiles  Nov 1 Javier  
13 Apply CS PUM33 and HR PUM 50 to PRD (Starting 2 pm) Nov 1 DBAs complete
14 Apply security for PRD (CS/HR) Nov 3 Security Admin complete
15 Backup Appsian/PS security DEV and TST (CS,HR,PORTAL) Nov 4 Security Admin complete
16 Refresh DEV from PRD (CS/HR/PORTAL)  Nov 7 -8  DBAs complete
17 Apply security for DEV (CS/HR/PORTAL)    Nov 12 Security Admin complete
18 Refresh TST from PRD (CS/HR/PORTAL)  Nov 13 - 14  DBAs In progress
19 Apply security for TST (CS/HR/PORTAL) Nov 15 Security Admin  