Patch Schedule - : CS/HR PeopleTool 8.61 Upgrade and CS PRP's

 

# Task Date Resource Status
1 Notify SA-team of patching schedule Jan 9 Patrick complete
2 Setup New Server for PeopleTool 8.61 Jan 27 - March 20 DBAs   In- Progress
3 SA Team Group -  Enable QA Portal Guard Tiles  Jan 9 Javier complete
4

Functional testing of patches in QA (CS/HR)

Jan 9 -  March 14

Functional Users/ ThoughtFocus

complete

5 SA Team Group - Remove QA Portal Guard Tiles  Apr 11 Javier  
6

Apply CS/HR PeopleTool 8.61 Upgrade to PRD (Start 2 PM)

March 21 - 23

ThoughtFocus

complete
7 Apply security for PRD (CS/HR) March 23 Security Admin  
8 Backup Appsian/PS security DEV and TST (CS/HR)  March 28 Security Admin  
9 Refresh DEV from PRD (CS/HR)  TBD  DBAs  
10 Apply security for DEV (CS/HR)    TBD Security Admin  
11 Refresh TST from PRD (CS/HR)  TBD  DBAs  
12 Apply security for TST (CS/HR)  TBD Security Admin  
13 Refresh QA from PRD (CS/HR)  TBD  DBAs  
14 Apply security for QA (CS/HR)  TBD Security Admin  

Created: 01/09/2025
Updated: 03/31/2025