Patch Schedule 10/28/17 - 4/9/18

 

# Task Date Resource Status
1 Prep for patches/fixes 4/3 - 4/6  DBAs Done
2 Apply Bundle# 48 and FA fixes to CS90UPG 4/ 11 - 4/13 Functional Users Done
3  Apply Security for FA Fixes in CS90UPG  4/13 Gilbert Done
4 Functional testing of Bundle# 48 and FA Fixes in CS90UPG  4/16 - 4/24 Functional Users Done
5 Freeze project Moves from Development to PRD (CS) 3/19 - 5/18 DBAs Done
6 Apply Bundle# 48 and FA Fixes to PRD (CS) (Start at noon) 4/27 - 4/29 DBAs Done
7 Security for Bundle# 48 and FA Fixes on PRD (CS) 4/29 Gilbert Done
8 Refresh DEV from PRD (CS/HR)  5/3 -5/9  DBAs Done
9 Apply security for DEV (CS/HR) 5/10 Gilbert Done
10 Refresh TST from PRD (CS/HR) 5/14 - 5/15 DBAs Done
11 Apply security for TST (CS/HR) 5/15 Gilbert Done
12 Refresh QA for PRD(CS/HR) 5/14 refresh 5/16 - 5/17 DBAs Done
13 Apply security for QA (CS/HR) 5/17 - 5/18 Gilbert Done

Created:  4/6/18
Updated: 5/16/18